CITY OF JOHANNESBURG’S DEBT RELIEF PROGRAMME
The City of Johannesburg (“the City”) launched Phase 4 of its Debt Relief Programme (“DRP”), running from 1 November 2025 to 31 October 2026. All applications must be made before 31 October 2026 in order to qualify.
The DRP offers up to a 50% debt write-off, together with 100% waivers of interest and penalty fees. Depending on the applicant’s category (discussed below) and ability to pay, relief may take the form of a partial or full write-off, coupled with a payment arrangement for any remaining balance.
Taking part in the DRP will not affect a customer’s credit score negatively. However, before any debt write-off is processed, customers are required to enter and sign an Acknowledgement of Debt (“AOD”), setting out the agreed repayment terms. Failure to maintain payments for the outstanding debt may result in the City taking credit control measures, such as disconnections of municipal services, and recovery measures to recover the entire outstanding balance.
The DRP is open to several categories of municipal account holders, some benefitting more than others. Below is a practical breakdown of who may qualify and what each category of applicant stands to gain.
PENSIONERS AND ESP (EXTENDED SOCIAL PACKAGE) BENEFICIARIES
Qualifying criteria:
Relief offered:
RESIDENTIAL CUSTOMERS (ALL INCOME LEVELS)
Qualifying criteria:
Relief offered:
SMALL BUSINESSES, FAITH-BASED ORGANISATIONS, NON-PROFIT ORGANISATIONS, OLD-AGE HOMES, ORPHANAGES AND BODIES CORPORATE
Qualifying criteria:
Relief offered:
LARGE BUSINESSES
Qualifying criteria:
Relief offered:
GENERAL CONDITIONS APPLICABLE TO ALL CATEGORIES
All categories also receive 100% interest and fee waivers in respect of final demands, disconnection notices, and other sundry charges.
Customers who have already received debt write-offs under previous City programmes are not eligible for the DRP. The sole exception is that pensioners and ESP customers may reapply if they continue to meet the qualifying conditions.
DRP AND EXTINCTIVE PRESCRIPTION
For large and small businesses, faith-based organisations, non-profit organisations, old-age homes, orphanages and bodies corporate, the DRP offers a 50% write-off of “qualifying debt older than 36 months.”
The choice of 36 months is difficult to overlook. Thirty-six months (or three years) is the exact extinctive prescription period for ordinary debts under section 11(d) of the Prescription Act 68 of 1969 (“Prescription Act”), after which an ordinary debt is no longer claimable by a creditor.
Extinctive prescription is the legal principle that a debt can no longer be claimed after a certain period has passed – in effect, the debt ‘expires’ by law.
This raises a fundamental question: why would a customer accept a 50% write-off of debt that is older than three years where the law of extinctive prescription already entitles a customer to a 100% extinction of the same debt?
EXTINCTIVE PRESCRIPTION AND MUNICIPAL CHARGES:
As a starting point, note that extinctive prescription does not apply equally to all types of debt. Certain debts remain claimable by a creditor for 30 years, such as property rates, sewer and refuse, while ordinary consumption charges such as electricity and water generally fall within the three-year prescription period.
The Prescription Act provides the statutory framework on prescription of debts, which can be summarised as follows:
As most municipalities impose a combination of charges to a single account, the total sum billed within a single month will ordinarily not constitute a single undifferentiated debt for purposes of extinctive prescription. The prescription period will depend on what the charge is for. Put simply, property rates and sewer charges generally sit in the 30-year category, while electricity and water consumption charges generally sit in the three-year category.
In general terms, if a municipal account has remained wholly unpaid in excess of three years, all water and electricity consumption charges older than three years on the account, including interest accrued thereon, will have become prescribed and are no longer legally claimable by the municipality. In contrast, all unpaid charges for property rates and sewer charges will remain claimable by the municipality.
PRESCRIPTION AND SECTION 102(2) OF THE MUNICIPAL SYSTEMS ACT – RINGFENCING DISPUTED AMOUNTS
In addition to the ordinary working of prescription (i.e., a debt remains unpaid for a period exceeding the debt’s prescription period), there exists an alternative method by which municipal consumption charges may become prescribed, and in practice is often the more important one. This alternative method arises from the interaction between section 102 of the Local Government: Municipal Systems Act 32 of 2000 (“Municipal Systems Act”) and the Prescription Act.
Section 102(1) of the Municipal Systems Act empowers municipalities to consolidate accounts, allocate payments to any account held by an account holder, and to implement credit control and debt collection measures.
Section 102(2) of the Municipal Systems Act places a limitation on the empowerment afforded in section 102(1), in that section 102(1) does not apply where there is a dispute between the municipality and an account holder concerning any specific amount claimed by the municipality from the account holder.
In practical terms, the limitation created by section 102(2) means that once a customer declares a dispute over specific charges, the municipality is prohibited from allocating incoming payments made by the customer to settle those disputed amounts. The charges are effectively “ringfenced”. If the ringfenced charges are ordinary debts such as electricity or water consumption charges, and more than three years pass without the City interrupting the running of prescription (Prescription can be ‘interrupted’ – meaning the clock resets – if the City issues a summons or obtains your acknowledgement that you owe the debt), those charges will become prescribed. This is so even if the customer continued making regular payments on the account to settle undisputed charges.
Our courts have in recent years addressed this issue repeatedly:
In Tarica and Another v City of Johannesburg Metropolitan Municipality¹, the court held that while the limitation created by section 102(2) remains operative, the City could not simply allocate incoming payments to the oldest charges on the account first. It was further held that electricity charges constitute ordinary debts under the Prescription Act and become prescribed after three years.
In BIR Investments (Pty) Ltd v City of Johannesburg Metropolitan Municipality², the City argued that section 102(2) prevented prescription from running, as the City is precluded from claiming the disputed amounts from the customer while a dispute persists.
The court rejected this contention, holding that section 102(2) does not prevent prescription from running or delay its completion, and that monthly payments for current and undisputed charges do not amount to an admission of liability for disputed charges.
This position was reaffirmed as recently as July 2026 in Hlabangana v City of Johannesburg Metropolitan Municipality³, where the court held that payment of current charges on a monthly basis did not interrupt the running of prescription on disputed amounts.
CHOOSING THE RIGHT ROUTE: DRP OR PRESCRIPTION
The DRP offers a 50% write-off on qualifying debt older than 36 months. However, as the foregoing analysis demonstrates, the law of extinctive prescription may entitle consumers to a 100% write-off of electricity and water consumption charges older than three years, without a customer being required to enter an AOD or being subject to the DRP’s restrictions and conditions.
Prescription is not an automatic or blanket entitlement. The customer must be able to show that all the legal requirements for prescription have been met—this is the customer’s responsibility, not the City’s. Even so, where a municipal account has been in dispute, and the City has neither resolved the dispute nor issued summons for more than three years, our courts have held that consumption charges will become prescribed in the appropriate circumstances.
While a 100% write-off of municipal debt may sound like the more attractive option, there are several considerations that one would need to take into account before claiming prescription, including the onus of proving the elements of extinctive prescription, and more often than not High Court litigation.
DRP ADVANTAGES
DRP DISADVANTAGES
PRESCRIPTION CLAIM ADVANTAGES
PRESCRIPTION CLAIM DISADVANTAGES
CONCLUSION
For a customer whose arrears are made up mainly of historic electricity and water consumption charges, and who has a continuing, well-documented dispute with the City, a prescription claim may deliver substantially more relief than the DRP. However, for customers whose arrears include substantial property rates and sewer charges, the DRP may be the more pragmatic route to obtain relief across all billing items on an account, if such charges are included by the City as “qualifying debt”.
There is no clear option that will benefit all customers. Each customer’s account, payment history, dispute record, and financial position must be assessed on its own facts. Where the amounts are significant, obtaining legal advice before making a decision is advisable.
ABOUT THE CASES CITED AND OUR ROLE:
HBGSchindlers Attorneys and Notaries acted on behalf of the successful applicants in the cases cited herein. These judgments represent important victories for ratepayers and property owners in Johannesburg in clarifying that Section 102(2) of the Systems Act does not suspend the running of prescription.
Our firm continues to lead in municipal law and billing dispute litigation, protecting clients from unlawful billing practices and ensuring that municipalities comply with their statutory and constitutional obligations.
¹ Tarica and Another v City of Johannesburg Metropolitan Municipality (2023/044543) [2024] ZAGPJHC 46 (27 January 2025)
² BIR Investments (Pty) Ltd v City of Johannesburg Metropolitan Municipality (2023/049538) [2025] ZAGPJHC 1050 (20 October 2025)
³ Hlabangana v City of Johannesburg Metropolitan Municipality (2024/947995) [2026] ZAGPJHC 841 (22 July 2026)